Determine the Critical Path given the following information:
| Activity | Time | Precedence Activities |
| A | 3 | None |
| B | 5 | None |
| C | 2 | A,B |
| D | 6 | C |
| E | 5 | C |
| F | 3 | E |
| G | 4 | C |
| H | 3 | D,G,F |
| I | 4 | D,F |
| J | 2 | H |
| K | 2 | I,J |
If you needed to crash the project, which Activity would you work on first?