Question: Doing activities in parallel that normally would be done sequentially in order to compress the schedule describes which of the following? Fast tracking Resource Leveling

Doing activities in parallel that normally would be done sequentially in order to compress the schedule describes which of the following?
Fast tracking
Resource Leveling
Crashing
Resource Loading