Question: Draw an Activity-on-Node Diagram, identify activity duration, slack for each activity, project duration, and project critical path for the following: Activity Name Predecessor(s) a m
- Draw an Activity-on-Node Diagram, identify activity duration, slack for each activity, project duration, and project critical path for the following:
| Activity Name | Predecessor(s) | a | m | b |
| A | None | 20 | 50 | 90 |
| B | None | 10 | 30 | 40 |
| C | None | 10 | 20 | 30 |
| D | A | 20 | 10 | 30 |
| E | B,C | 10 | 20 | 30 |
| F | C,D | 20 | 30 | 60 |
| G | F | 10 | 20 | 50 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts