Question: Draw an Activity-on-Arrow Diagram, identify project duration, slack for each activity, and project critical path for the following: Activity Name Predecessor(s) Duration (Weeks) A None

  1. Draw an Activity-on-Arrow Diagram, identify project duration, slack for each activity, and project critical path for the following:

Activity Name

Predecessor(s)

Duration (Weeks)

A

None

20

B

None

10

C

None

10

D

A,B

40

E

C

10

F

C,D

20

G

E,F

10

Step by Step Solution