Question: Duration Activity Predecessor Optimistic Most Likely Pessimistic tool te Citical (Y/N)? A 8 14 20 14 4 2 Y B A 3 12 21 12

Duration Activity Predecessor Optimistic Most

Duration Activity Predecessor Optimistic Most Likely Pessimistic tool te Citical (Y/N)? A 8 14 20 14 4 2 Y B A 3 12 21 12 9 3 Y B 8 11 14 11 1 1 n D B 6 6 6 6 0 0 Y E B 8 14 20 14 4 2 n F CD 8 11 11 1 1 n 14 25 G D 4 10 12.25 3.5 11.5 10 . EG 4 10 16 4 2 Part 3 - Given the information for this project, which activity(ies) are the most worrisome for the project manager explain your answer for each activity you choose to include here. If you are pointing out more than one activity, start the list with the top most and then go down your list