Question: During the Identify Risk Process, the project manager and the team categorize risks in an effort to determine risks they may have missed. Of the
During the Identify Risk Process, the project manager and the team categorize risks in an effort to determine risks they may have missed. Of the following, which is the best example of risk categories?
Group of answer choices
External, internal, technology, personnel
Initiating, planning, executing, monitoring and controlling, closing
Scope, time, cost
Quality, schedule, budget