Question: During the Identify Risk Process, the project manager and the team categorize risks in an effort to determine risks they may have missed. Of the
During the Identify Risk Process, the project manager and the team categorize risks in an effort to determine risks they may have missed. Of the following, which is the best example of risk categories?
a. Quality, schedule, budget
b. External, internal, technology, personnel
c. Scope, time, cost
d. Initiating, planning, executing, monitoring and controlling, closing
Step by Step Solution
3.48 Rating (155 Votes )
There are 3 Steps involved in it
The best example of risk categories for identifying missed risks is b External internal technology p... View full answer
Get step-by-step solutions from verified subject matter experts