Question: Estimate the duration of activity D using the PERT method, knowing that it has an optimistic time estimate of 3 days, a most likely estimate

  • Estimate the duration of activity D using the PERT method, knowing that it has an optimistic time estimate of 3 days, a most likely estimate of 4 days, and a pessimistic estimate of 11 days.
  • Draw a Network Diagram of this project.
  • Find the critical path and the shortest time to complete project
  • Calculate the ES, LS, EF, LF, and Slack time for each task in the network.

Estimate the duration of activity D using the PERT method, knowing that

\f

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Mathematics Questions!