Question: Estimate the duration of activity D using the PERT method, knowing that it has an optimistic time estimate of 3 days, a most likely estimate
- Estimate the duration of activity D using the PERT method, knowing that it has an optimistic time estimate of 3 days, a most likely estimate of 4 days, and a pessimistic estimate of 11 days.
- Draw a Network Diagram of this project.
- Find the critical path and the shortest time to complete project
- Calculate the ES, LS, EF, LF, and Slack time for each task in the network.