Question: Examine the following network diagram. List all possible sequences (chain/path) of activities and define the total duration for each path. There are 5 possible paths.

Examine the following network diagram. List all possible sequences (chain/path) of activities and define the total duration for each path. There are 5 possible paths. What is the critical path? Examine the following network diagram. List all
3 8 5 7 6 10 8 a 20 - " 1 2 3 13 s 4 7 9 12