Question: EXAMPLE (2 critical paths) ACTIVITY Predecessor Optimistic duration Most likely duration Pessimistic duration t 02 A 10 22 22 B 17 20 23 A,B 4

EXAMPLE (2 critical paths) ACTIVITY Predecessor

EXAMPLE (2 critical paths) ACTIVITY Predecessor Optimistic duration Most likely duration Pessimistic duration t 02 A 10 22 22 B 17 20 23 A,B 4 10 16 D A,B 2 14 32 E B,D 8 8 20 F 8 14 20 G D 10 22 22 H D,E 18 21 24 I F,G 4 16 28 - Calculate the probability of finishing the project 2 days late? - What is the project duration with a probabilty of 99%