Question: Table Q2: Project Activities Time Estimates (weeks) Activity ID Predecessor Optimistic duration Most likely duration Pessimistic Duration A - 1 4 7 B - 2

Table Q2: Project Activities Time Estimates (weeks)

Activity ID Predecessor Optimistic duration Most likely duration Pessimistic Duration
A - 1 4 7
B - 2 6 7
C B 3 3 6
D A 6 13 14
E A,C 3 6 12
F B 6 8 16
G E,F 1 5 6

(a)Draw a network diagram (A-o-N) for the project showing ES, EF, LS, LF, and slack for each activity.

(b) Determine the critical path and the project completion time.

(c) What is the probability of completing the project within 23 weeks?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!