Question: Find the critical path and the project completion time for the following list of activities. Calculate the probabilities of completing the following project in 13
- Find the critical path and the project completion time for the following list of activities. Calculate the probabilities of completing the following project in
- 13 days or more
- 11 days or less
- between 12 and 14 days
| Activity | Immediate Predecessor | Optimistic Duration | Most Probable Duration | Pessimistic Duration |
| A | - | 1 | 3 | 5 |
| B | - | 2 | 4 | 6 |
| C | A, B | 2 | 4 | 5 |
| D | A, B | 3 | 5 | 7 |
| E | C, D | 1 | 2 | 10 |