Question: Find the critical path and the project completion time for the following list of activities. Calculate the probabilities of completing the following project in 11
Find the critical path and the project completion time for the following list of activities. Calculate the probabilities of completing the following project in
- 11 days or less
- 12 days or less
- 13 days or more
- between 12 and 14 days
| Activity | Immediate Predecessor | Optimistic Duration | Most Probable Duration | Pessimistic Duration |
|---|---|---|---|---|
| A | - | 2 | 3 | 9 |
| B | - | 2 | 4 | 4 |
| C | A, B | 2 | 4 | 6 |
| D | A, B | 2 | 5 | 8 |
| E | C, D | 1 | 3 | 10 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
