Find the critical path and the project completion time for the following list of activities. Calculate the
Fantastic news! We've Found the answer you've been seeking!
Question:
- Find the critical path and the project completion time for the following list of activities. Calculate the probabilities of completing the following project in
- 13 days or more
- 11 days or less
- between 12 and 14 days
Activity | Immediate Predecessor | Optimistic Duration | Most Probable Duration | Pessimistic Duration |
A | - | 1 | 3 | 5 |
B | - | 2 | 4 | 6 |
C | A, B | 2 | 4 | 5 |
D | A, B | 3 | 5 | 7 |
E | C, D | 1 | 2 | 10 |
Related Book For
Project Management A Managerial Approach
ISBN: 978-0470226216
7th Edition
Authors: Jack R. Meredith, Samuel J. Mantel,
Posted Date: