Question: Find the critical Path Task Duration Depends on T1 1 T2 3 T3 5 T4 3 T1 T5 2 T1 T6 2 T1,T3 T7 3
Find the critical Path
| Task | Duration | Depends on |
|---|---|---|
| T1 | 1 | |
| T2 | 3 | |
| T3 | 5 | |
| T4 | 3 | T1 |
| T5 | 2 | T1 |
| T6 | 2 | T1,T3 |
| T7 | 3 | T2,T3 |
| T8 | 4 | T4,T5,T6 |
| T9 | 3 | T5,T7 |
| T10 | 2 | T7 |