Question: Find the critical Path Task Duration Depends on T1 1 T2 3 T3 5 T4 3 T1 T5 2 T1 T6 2 T1,T3 T7 3

Find the critical Path

Task Duration Depends on
T1 1
T2 3
T3 5
T4 3 T1
T5 2 T1
T6 2 T1,T3
T7 3 T2,T3
T8 4 T4,T5,T6
T9 3 T5,T7
T10 2 T7