Question: Find the project duration & critical path: Activity Duration (Weeks) Immediate Predecessors A 10 B 4 C 6 D 4 B E 1 C,D F

Find the project duration & critical path: Activity Duration (Weeks) Immediate Predecessors A 10 B 4 C 6 D 4 B E 1 C,D F 4 C G 4 A,D H 5 E,F Project Schedule Path Duration A-G 10+4 = 14 weeks B-D-G 4+4+4 = 12 weeks B-D-E-H 4+4+1+5 = 14 weeks C-E-H 6+1+5 = 12 weeks C-F-H 6+4+5 = 15 weeks If C-F-H is the critical path at 15 weeks. Using the network diagram and project schedule that you created. Determine what is the latest finish time for Activity - "G"? a. 10 b. 11 c. 14 d. 15

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!