Question: For the given data find out the critical path and the duration in which the project will be completed. Also find out the ES ,

For the given data find out the critical path and the duration in which the project will be completed. Also find out the ES, EF, LS, LF and total float. 3. What is the difference between CPM and PERT? 4. What is the concept of crashing? 5. What is the difference between optimistic, pessimistic and most likely times in PERT? 6. What is the ES, EF, LS, LF and Total float?
Activity Predecessor Duration (days) A ---2 B ---1 C A 3 D B 2 E B 1 F C,D 3 G C,D 1 H E,F 4