Question: 7.69 pts For the given problem, Task Predecessor Normal Crash Normal Crash Time Cost Cost Time A 3 2 40 120 B 7 5 80

7.69 pts For the given problem, Task Predecessor Normal Crash Normal Crash Time Cost Cost Time A 3 2 40 120 B 7 5 80 30 45 , 5 4 90 D 6 5 30 50 E B, C 4 2. 40 100 F DE 5 4 55 75 Answer the following questions: a. What is the normal cost of the project? [Select] b. Which activity would you crash first to reduce the project by one day and what will be the cost to crash? [Select] c. Which activity would you crash next by an additional day and what would be the total 2 day cost of crashing? [Select]