Question: From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many
From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take?
| ID | Description | Predecessor | Time |
| A | Survey site | None | 6 |
| B | Excavate site | A | 6 |
| C | Install power lines | B | 4 |
| D | Install drainage | B | 1 |
| E | Pour foundation | C, D | 3 |
1 the project will take
2.the critical patch is
3 the late start on activity c is
theslack start on c is
slac