Question: From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many
From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take?
ID Description Predecessor Duration
A Survey site None 4
B Install drainage A 6
C Install power lines B 2
D Excavate site B 3
E Pour foundation C,D 4
- How many days will the project take?
- What is the early start on activity E