Question: From the following information. develop an AON project network. Complete the fowvard and backward pass, compute activity slack, and identify the critical path. How many

 From the following information. develop an AON project network. Complete the

From the following information. develop an AON project network. Complete the fowvard and backward pass, compute activity slack, and identify the critical path. How many days will the project take? ID Description Predecessor Time A Survey site None 6 B Excavate site A 6 C Install power Lines B 2 D Install. drainage B 3 E Pour foundation C, D 4 arr~ ' . H W