Question: From the project plan, we that a project has a total budgeted cost of $920,084 and a project completion time of 16 weeks. At the

From the project plan, we that a project has a
From the project plan, we that a project has a total budgeted cost of $920,084 and a project completion time of 16 weeks. At the moment, the project has been in a performing stage. At the end of week 8 , the project progress report shows that the project has consumed a total of $310,111, the project cumulative earned value is $342,413, and the project schedule performance index is 0.91. What is the value of the project schedule variance at the end of week 8 ? Use at least 4 decimals