From the project plan, we that a project has a total budgeted cost of $545,902 and a project completion time of 16 weeks. At the moment, the project has been in a performing phase. At the end of week 6 , the project progress report shows that the project has consumed a total of $290,543, the project schedule variance is $62,771 and the project schedule variance is $36,320. What is the project cost performance index at the end of week 6? Use at least 4 decimals