Question: From the project plan, we that a project has a total budgeted cost of $547,848 and a project completion time of 16 weeks. At the
From the project plan, we that a project has a total budgeted cost of $547,848 and a project completion time of 16 weeks. At the moment, the project has been in a performing phase. At the end of week 8, the project progress report shows that the project has consumed a total of $287,701, the project schedule variance is $43,481 and the project schedule variance is $27,822.
What is the estimated project cost at completion if the project continues at the cost performance index observed at the end of week 8?
Use at least 4 decimals.