Question: From the project plan, we that a project has a total budgeted cost of $677,924 and a project completion time of 16 weeks. At the

From the project plan, we that a project has a
From the project plan, we that a project has a total budgeted cost of $677,924 and a project completion time of 16 weeks. At the moment, the project has been in a performing phase. At the end of week 6 , the project progress report shows that the project has consumed a total of $276,109, the project schedule variance is $59,049 and the project schedule variance is $37,743. What is the project cost performance index at the end of week 6 ? Use at least 4 decimals