Question: From the project plan, we that a project has a total budgeted cost of $947,150 and a project completion time of 16 weeks. At the

From the project plan, we that a project has a
From the project plan, we that a project has a total budgeted cost of $947,150 and a project completion time of 16 weeks. At the moment, the project has been in a performing stage. At the end of week 7 , the project progress report shows that the project has consumed a total of $317,662, the project cumulative earned value is $344,908, and the project schedule performance index is 0.83. What is the value of the project schedule variance at the end of week 7 ? Use at least 4 decimals