Question: From the project plan, we that a project has a total budgeted cost of $528,599 and a project completion time of 16 weeks. At the

From the project plan, we that a project has a
From the project plan, we that a project has a total budgeted cost of $528,599 and a project completion time of 16 weeks. At the moment, the project has been in a performing phase. At the end of week 7 , the project progress report shows that the project has consumed a total of $285.812, the project schedule variance is $53,602 and the project schedule variance is $34,540. What is the project cost performance index at the end of week 7? Use at least 4 decimals