Question: Given a simple project illustrated in the following table Activity Immediate Predecessors Time ( weeks ) 1 - 2 2 1 3 3 2 4

Given a simple project illustrated in the following table
Activity Immediate Predecessors Time (weeks)
1-2
213
324
422
542
Assume that "Activity 1" actually finished at 3 weeks, and "Activity 2" actually finished at 6 weeks. Given the actual project progress, what is the ES (earliest start time) of "Activity 5"?
Group of answer choices
9
11
10
8