Question: Given a simple project illustrated in the following table Activity Immediate Predecessors Time (weeks) 1 - 2 2 - 3 3 1, 2 2 4
Given a simple project illustrated in the following table
| Activity | Immediate Predecessors | Time (weeks) |
| 1 | - | 2 |
| 2 | - | 3 |
| 3 | 1, 2 | 2 |
| 4 | 3 | 5 |
| 5 | 3 | 4 |
The required project completion time is 12. Assume that "Activity 1" actually finished at 3 weeks, and "Activity 2" actually finished at 2 weeks. Given the actual project progress, what is the LF (lastest time) of "Activity 4"?