Question: Given a simple project illustrated in the following table Activity Immediate Predecessors Time (weeks) 1 - 2 2 1 3 3 2 2 4 2
Given a simple project illustrated in the following table
| Activity | Immediate Predecessors | Time (weeks) |
| 1 | - | 2 |
| 2 | 1 | 3 |
| 3 | 2 | 2 |
| 4 | 2 | 5 |
| 5 | 4 | 4 |
Assume that "Activity 1" actually finished at 2 weeks, and "Activity 2" actually finished at 6 weeks. Given the actual project progress, what is the expected project completion time?