Question: Given a simple project illustrated in the following table Activity Immediate Predecessors Time (weeks) 1 - 2 2 1 3 3 2 2 4 2

Given a simple project illustrated in the following table

Activity Immediate Predecessors Time (weeks)
1 - 2
2 1 3
3 2 2
4 2 5
5 4 4

Assume that "Activity 1" actually finished at 2 weeks, and "Activity 2" actually finished at 6 weeks. Given the actual project progress, what is the expected project completion time?