Question: Given a simple Project like the one pictured above. Optimistic / Most Likely / Pessimist Times were assessed and Path Means and Path Standard Deviations

Given a simple Project like the one pictured above. Optimistic / Most Likely / Pessimist Times were assessed and Path Means and Path Standard Deviations were calculated. For Path 1-2-5 we have a Path Mean = 30 and a Path Standard Deviation = 5. For Path 1-3-4-5 we have a Path Mean = 32 and a Path Standard Deviation = 4. Determine both the Probability that Path 1-2-5 will finish in 32 Days or Less and the Probability that the Project will finish in 32 Days or Less.

Question 5 options:

0.655421697 : 0.327710848
0.84134474 : 0.65067307
0.964069734 : 0.925449956
0.986096601 : 0.974042129

Given a simple Project like the one pictured above. Optimistic / Most Likely / Pessimist Times were assessed and Path Means and Path Standard Deviations were calculated. For Path 1-2-5 we have a Path Mean = 30 and a Path Standard Deviation = 5. For Path 1-3-4-5 we have a Path Mean = 32 and a Path Standard Deviation = 4. Determine both the Probability that Path 1-2-5 will finish in 32 Days or Less and the Probability that the Project will finish in 32 Days or Less.

Question 5 options:

0.655421697 : 0.327710848
0.84134474 : 0.65067307
0.964069734 : 0.925449956
0.986096601 : 0.974042129

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!