Question: Given a simple Project like the one pictured above. Optimistic / Most Likely / Pessimist Times were assessed and Path Means and Path Standard Deviations
Given a simple Project like the one pictured above. Optimistic / Most Likely / Pessimist Times were assessed and Path Means and Path Standard Deviations were calculated. For Path 1-2-5 we have a Path Mean = 33 and a Path Standard Deviation = 4. For Path 1-3-4-5 we have a Path Mean = 33 and a Path Standard Deviation = 3. Determine both the Probability that Path 1-2-5 will finish in 33 Days or Less and the Probability that the Project will finish in 33 Days or Less.
Question 5 options:
| 0.5 : 0.25 | |
| 0.84134474 : 0.764604608 | |
| 0.959940886 : 0.950518772 | |
| 0.894350161 : 0.851608871 |