Question: Given a simple Project like the one pictured above. Optimistic / Most Likely / Pessimist Times were assessed and Path Means and Path Standard Deviations

Given a simple Project like the one picturedGiven a simple Project like the one pictured above. Optimistic / Most Likely / Pessimist Times were assessed and Path Means and Path Standard Deviations were calculated. For Path 1-2-5 we have a Path Mean = 27 and a Path Standard Deviation = 5. For Path 1-3-4-5 we have a Path Mean = 25 and a Path Standard Deviation = 4. Determine both the Probability that Path 1-2-5 will finish in 27 Days or Less and the Probability that the Project will finish in 27 Days or Less.

Question 3 options:

0.977249938 : 0.975930683

0.5 : 0.345731234

0.788144666 : 0.735490905

0.986096601 : 0.985527538

2 S 3

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!