Question: Given a simple Project like the one pictured above. Optimistic / Most Likely / Pessimist Times were assessed and Path Means and Path Standard Deviations
Given a simple Project like the one pictured above. Optimistic / Most Likely / Pessimist Times were assessed and Path Means and Path Standard Deviations were calculated. For Path 1-2-5 we have a Path Mean = 27 and a Path Standard Deviation = 5. For Path 1-3-4-5 we have a Path Mean = 25 and a Path Standard Deviation = 4. Determine both the Probability that Path 1-2-5 will finish in 27 Days or Less and the Probability that the Project will finish in 27 Days or Less.
Question 3 options:
| 0.977249938 : 0.975930683 | |
| 0.5 : 0.345731234 | |
| 0.788144666 : 0.735490905 | |
| 0.986096601 : 0.985527538 |