Question: Question 5 (4 points) Given a simple Project like the one pictured above. Optimistic / Most Likely / Pessimist Times were assessed and Path Means
Question 5 (4 points)
Given a simple Project like the one pictured above. Optimistic / Most Likely / Pessimist Times were assessed and Path Means and Path Standard Deviations were calculated. For Path 1-2-5 we have a Path Mean = 32 and a Path Standard Deviation = 5. For Path 1-3-4-5 we have a Path Mean = 35 and a Path Standard Deviation = 3. Determine both the Probability that Path 1-2-5 will finish in 35 Days or Less and the Probability that the Project will finish in 35 Days or Less.
Question 5 options:
| 0.84134474 : 0.628911531 | |
| 0.725746935 : 0.362873467 | |
| 0.788144666 : 0.496971394 | |
| 0.884930268 : 0.744531427 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts