Question: Given a simple Project like the one pictured above. Optimistic / Most Likely / Pessimist Times were assessed and Path Means and Path Standard Deviations
Given a simple Project like the one pictured above. Optimistic / Most Likely / Pessimist Times were assessed and Path Means and Path Standard Deviations were calculated. For Path 1-2-5 we have a Path Mean = 30 and a Path Standard Deviation = 5. For Path 1-3-4-5 we have a Path Mean = 32 and a Path Standard Deviation = 4. Determine both the Probability that Path 1-2-5 will finish in 32 Days or Less and the Probability that the Project will finish in 32 Days or Less.
Question 5 options:
| 0.655421697 : 0.327710848 | |
| 0.84134474 : 0.65067307 | |
| 0.964069734 : 0.925449956 | |
| 0.986096601 : 0.974042129 |
Given a simple Project like the one pictured above. Optimistic / Most Likely / Pessimist Times were assessed and Path Means and Path Standard Deviations were calculated. For Path 1-2-5 we have a Path Mean = 30 and a Path Standard Deviation = 5. For Path 1-3-4-5 we have a Path Mean = 32 and a Path Standard Deviation = 4. Determine both the Probability that Path 1-2-5 will finish in 32 Days or Less and the Probability that the Project will finish in 32 Days or Less.
Question 5 options:
| 0.655421697 : 0.327710848 | |
| 0.84134474 : 0.65067307 | |
| 0.964069734 : 0.925449956 | |
| 0.986096601 : 0.974042129 |