Question: Given an activity in a smartphone design project whose planned cost was $13,000 but actual cost to date is $12,000 so far, and whose value

Given an activity in a smartphone design project
Given an activity in a smartphone design project whose planned cost was $13,000 but actual cost to date is $12,000 so far, and whose value completed is only 80%, calculate the cost and schedule variances. Will the client be pleased or angry