Question: Given is a CPM project network diagram as shown below. ActivityStartABCDEFGHEndday0237556840 a) The Project Completion time = Blank 1 days. b) The Earliest Start time,
Given is a CPM project network diagram as shown below.
ActivityStartABCDEFGHEndday0237556840
a) The Project Completion time = Blank 1 days.
b) The Earliest Start time, ES, of Activity G = Blank 2 days.
c) The Latest Finish time, LF, of Activity C = Blank 3 days.
d) The critical activities are = Blank 4 (ex. Fill in the answer as: ABCD)