Question: Given is a PERT project network diagram as shown below. table [ [ Activity , Start,A , B , C , D , E

Given is a PERT project network diagram as shown below.
\table[[Activity,Start,A,B,C,D,E,F,G,H,End],[Time,0,1.58,2.68,2.56,1.89,3.21,3.83,2.30,3.00,O]]
a) The Project Completion time =(in 2 decimal places)
b) The Earliest Start time, ES, of Activity G =(in 2 decimal places)
c) The Latest Finish time, LF, of Acitivity C=(in 2 decimal
places)
d) The critical activities are = ex. type in critical activities as +-BCD, no comma, no space)Given is a Project with network diagram and activity times as shown below.
\table[[Activity,A,B,C,D,E,F,G,H,1,1],[Time (wks),10,5,6,16,3,15,12,5,8,6]]
a) The Earliest Start (ES) time of Activity I = Question Blank 1 of 6 weeks
b) The Latest Start (LS) time of Activity B = Question Blank 2 of 6 weeks
c) The Slack time of Activity C = Question Blank 3 of 6 weeks
d) The Earliest Finish (EF) time of Activity H= Question Blank 4 of 6 weeks
e) The Latest Finish (LF) time of Activity B = Question Blank 5 of 6 weeks
f) The Project Completion time = Question Blank 6 of 6 weeks
Given is a PERT project network diagram as shown

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!