Question: Given is a CPM project network diagram as shown below. Start End Activity Start A B C D E F G H End day on

Given is a CPM project network diagram as shown
Given is a CPM project network diagram as shown below. Start End Activity Start A B C D E F G H End day on 27 3 4 5 6 307 a) The Project Completion time = b) The Earliest Start time, ES, of Activity G = days c) The Latest Finish time, LF, of Acitivity C= days d) The critical activities are = (ex. Fill in answer as: ABCD)