Question: Given is a CPM project network diagram as shown below. Start End B D A 19 H Activity day Start 0 B 6 4 D

Given is a CPM project network diagram as shown
Given is a CPM project network diagram as shown below. Start End B D A 19 H Activity day Start 0 B 6 4 D 7 E 8 F 2 G 5 End 0 3 a) The Project Completion time - days. b) The Earliest Start time, ES of Activity G = days c) The Latest Finish time, LF, of Acitivity C - days. d) The critical activities are - (ex. Fill in answer as: ABCD)