Question: Given is a CPM project network diagram as shown below. Start Stare End A G H Activity day Start 0 B 8 C 3 D

Given is a CPM project network diagram as shown

Given is a CPM project network diagram as shown below. Start Stare End A G H Activity day Start 0 B 8 C 3 D 5 E 6 F 8 End 0 5 | | | | | 3 4 | a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G = days. c) The Latest Finish time, LF, of Acitivity C= days. d) The critical activities are = (ex. Fill in answer as: ABCD)