Question: Given is a CPM project network diagram as shown below. Start End Activity day Start 0 A 5 B 9 C 4 D 7 E

Given is a CPM project network diagram as shown

Given is a CPM project network diagram as shown below. Start End Activity day Start 0 A 5 B 9 C 4 D 7 E 4 F 8 G 6 H 8 End 0 a) The Project Completion time = 30 days. For Blank 1 b) The Earliest Start time, ES, of Activity G- 10 days. c) The Latest Finish time, LF, of Acitivity C= 14 days. d) The critical activities are = BDGH (ex. Fill in answer as: ABCD)