Question: QUESTION 1 Given is a CPM project network diagram as shown below. A F Start E H End B D G Activity Start days A

QUESTION 1 Given is a CPM project network diagram
QUESTION 1 Given is a CPM project network diagram as shown below. A F Start E H End B D G Activity Start days A 0 B 5 4 5 D 7 E 6 F 6 G 5 H 6 End 0 a) The Project Completion time = days b) The Earliest Start time, ES, of Activity G = days. c) The Latest Finish time, LF, of Acitivity C = days d) The critical activities are = (ex. Fill in answer as: ABCD)