Question: QUESTION 5 Given is a CPM project network diagram as shown below. A F Start E H End B D Start A B E H

QUESTION 5 Given is a CPM project network diagram
QUESTION 5 Given is a CPM project network diagram as shown below. A F Start E H End B D Start A B E H End Activity day 7 D 3 F 5 G 6 0 2 4 3 0 a) The Project Completion time = days. b) The Earliest Start time, Es, of Activity G = days. c) The Latest Finish time, LF, of Acitivity C - days. d) The critical activities are (ex. Fill in answer as: ABCD)