Question: Given that the AC = 500, PV = 400 and EV = 300, this project is currently _________ budget and ______ schedule. under, ahead of

Given that the AC = 500, PV = 400 and EV = 300, this project is currently _________ budget and ______ schedule.

  • under, ahead of

  • under, behind

  • over, behind

  • over, ahead of

  • on, on