Question: Given the activities whose sequence is described by the following table, draw the appropriate activity-on-node (AON) network diagram. a -- 5 b a 2 c

Given the activities whose sequence is described by the following table, draw the appropriate activity-on-node (AON) network diagram.

a -- 5

b a 2

c a 4

d b 5

e b 5

f c 5

g e.f 2

h d 3

i g,h 5