Question: Given the following data for the tasks in a production process, which of the following tasks have non - zero slack times? Task name Duration

Given the following data for the tasks in a production process, which of the following tasks have non-zero slack times?
Task name
Duration (days)
Immediate Predecessor
A
5
-
B
2
A
C
3
A, B
D
3
A
E
4
D
F
2
C, E
F
E
D
C