Question: Given the following highway rerouting project, table [ [ Activity , table [ [ Immediate ] , [ predecessor ] ] ,

Given the following highway rerouting project,
\table[[Activity,\table[[Immediate],[predecessor]],\table[[Activity time],[(Months)]]],[A: Schedule crew,-,4],[B: Schedule equipment,-,6],[C: Plan new route,A,2],[D: Costs meet budget?,B,6],[E: Inform public,C,B,3],[F: Put out signs,C,B,3],[G: Begin rerouting,D,E,5]]
a)Draw the network diagram(AOA ,AON)(b) Find the ESs, LSs, and slacks. (c) Find the critical path (d) If the project has a 11/2-year deadline for reopening, should we consider crashing some activities? Explain.
 Given the following highway rerouting project, \table[[Activity,\table[[Immediate],[predecessor]],\table[[Activity time],[(Months)]]],[A: Schedule crew,-,4],[B: Schedule

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!