Question: Given the following information for a project, draw the AON (Activity-On-Node) project network to determine the following: 1. What is the critical path? 2. What

Given the following information for a project, draw the AON (Activity-On-Node) project network to determine the following:

1. What is the critical path? 2. What is the project duration?

3. State what activities have slack and how much slack each has.

Activity Immediate Processor Activity Time (days)
A - 6
B A 8
C - 5
D A, B 4
E C 7
F C, D 3
G D 6
H E, F 5