Question: Given the following information for a project, draw the AON (Activity-On-Node) project network to determine the following: 1. What is the critical path? 2. What
Given the following information for a project, draw the AON (Activity-On-Node) project network to determine the following:
1. What is the critical path? 2. What is the project duration?
3. State what activities have slack and how much slack each has.
| Activity | Immediate Processor | Activity Time (days) |
| A | - | 6 |
| B | A | 8 |
| C | - | 5 |
| D | A, B | 4 |
| E | C | 7 |
| F | C, D | 3 |
| G | D | 6 |
| H | E, F | 5 |