Question: Given the following information for a project, draw the AON (Activity-On-Node) project network to determine the following: 1. What is the critical path? 2. What

Given the following information for a project,

Given the following information for a project, draw the AON (Activity-On-Node) project network to determine the following: 1. What is the critical path? 2. What is the project duration? 3. State what activities have slack and how much slack each has. Immediate Activity Time Activity Processor (days) 6 A B 8 5 D 4 E 7 F A B CD D, E, F E 3 G 6 H 5